Over the years, repeated concerns were raised regarding the safety of the Village’s sidewalk system. In particular, were sidewalk-tripping hazards in the older part of town. To address these concerns, the Village provided two options to eliminate these hazards. The first step was to repair the tripping hazard by using asphalt patch material or by grinding the sidewalk to provide a smooth surface. This step was always taken whenever a tripping hazard was reported. Unfortunately, too often this approach left the resident dissatisfied with both the repair and the general appearance of their sidewalk. To address the concern of appearance, the Village developed a 50/50 Sidewalk Repair Program designed to replace the asphalt-repaired sidewalk as well as any other defects that could raise a safety issue. Under this program the cost of replacing sidewalk was shared evenly between the resident and the Village.

In reviewing the history of sidewalk complaints received over the  years, it was noted that more than 88% of these complaints pertained to tripping hazards caused by a vertical displacement. Clearly, the number one concern in the community, at this time, is to eliminate vertical displacements that could result in tripping. In response, the Village Council appropriate $250,000 in 2001 as a first step towards implementing a program designed to repair all sidewalks in the Village that posed a tripping hazard. The design of this program is such that the worst tripping hazards throughout the Village were addressed first. 

Based upon the extent of the sidewalk problem, the criteria in place to identify tripping hazards, as well as, the funding level provided, the Hazardous Sidewalk Repair Program has the following parameters:

The Village has been divided into nine areas that will be inspected once every nineive years. Click Here to See Map.
 

  1. The initial inspection of each area will focus on vertical displacements of 7/8" or greater.
  2. If replacement of sidewalk is required due to vertical displacement, adjacent sidewalk will also be inspected for other replacement criteria.
  3. All asphalt-repaired sidewalks will be replaced as part of this program.
  4. All cost associated with the replacement of these sidewalks will be the sole responsibility of the Village.
     

RELATIONSHIP TO 50/50 SIDEWALK REPAIR PROGRAM

Although the Hazardous Sidewalk Program is designed to identify and replace all hazardous sidewalks throughout the community, there will still be a need to maintain the existing 50/50 Sidewalk Repair Program. Over the next four years, tripping hazards in those neighborhoods not scheduled for inspection and repair will still need to be addressed. Therefore, the existing repair program will remain in place (asphalt patching or grinding to eliminate the hazard). Once completed, the resident will have the option of participating in the 50/50 Sidewalk Replacement Program or wait until these asphalt repaired sidewalks are picked up under the Hazardous Sidewalk Replacement Program.

It is anticipated that at some future date, the 50/50 Sidewalk Replacement Program could be phased out. This would occur when the quantity of sidewalk needing replacement falls to a level thereby allowing all sidewalk requests to be included as part of the Hazardous Sidewalk Replacement Program for any given year. However, until such time, the 50/50 Sidewalk Repair Program will remain in place in order to provide Village residents the greatest amount of service and safety.

If you have or wish to report a hazardous sidewalk, please call Public Works at (847) 705-5200.
 

 
 

Village Hall Regular Hours: Monday - Friday: 8:00 AM - 5:00 PM
200 East Wood Street, Palatine, Illinois 60067 P. (847) 358-7500
Emergency:911 Non-Emergency: (847) 359-9000 Hours: 24 Hours
Police Headquarters 595 North Hicks Road, Palatine, Illinois 60067
© 2014 The Village of Palatine. All Rights Reserved.